Accelerated Bridge Program Design/Bid/Build Phase 1A

Contracts:

Accelerated Bridge Program Phase IA Highlights

Number of Bridge Deck Replacements
77
Number of Replacement Bridges
3
Number of Bridges with improved load rating
45
Number of Bridges Utilizing Precast Decks
14
Number of Bridges utilizing Accelerated Bridge Construction (ABC)
15
Number of Bridges will be completed in one weekend
5
Number of Bridges will be Completed in less than 2 weeks
6
Number of Abutments receiving jointless Details
104
Number of Bridges where Scuppers are completely Removed
20
Number of Bridges Utilizing Stainless Steel Deck Reinforcement
21